Laramie County Planning Commission Advances Wind Permit

On Nov. 12, 2026, the Laramie County Planning Commission voted unanimously to support Chalk Bluffs Energy's application for a Class C Conditional Use Permit (CUP), advancing the permit toward a final decision by the Board of County Commissioners scheduled for Tuesday, December 1, 2026, at 3:30 p.m.

The Planning Commission's action followed a recommendation from Laramie County Planning Staff, who, along with referral agencies, reviewed the application and determined that the wind component meets all criteria under the Laramie County Land Use Regulations and Comprehensive Plan.

About Chalk Bluffs Energy

Chalk Bluffs Energy is a subsidiary of Enyo Energy and represents a $1.67 billion energy generation project spanning Weld County, Colorado, and Laramie County, Wyoming. Construction is expected to begin in 2028, with the project fully operational by 2029.

Designed as an "All of the Above" energy project, Chalk Bluffs builds on the region's tradition of national leadership in domestic energy production. By combining multiple energy resources, the project is engineered to deliver reliable power to the regional electrical grid.

Total project capacity includes:

  • Wind Energy: Up to 500 megawatts

  • Solar Energy: Up to 500 megawatts

  • Natural Gas Reciprocating Engines: Up to 375 megawatts

  • Battery Storage: Up to 500 MWh

  • Transmission & Substations: 36 total miles of transmission lines, including 16 miles in Wyoming

The project currently holds permits for wind, solar, and battery storage in Weld County, Colorado. On the Wyoming side, Chalk Bluffs Energy is actively working to secure the necessary permits.

Laramie County Wind Component

Chalk Bluffs Energy is proposing no more than 12 wind turbines within Laramie County, making it the smallest wind project ever proposed in the county. Proposed turbine models include the Vestas V-163, a 322-foot hub-height turbine rated at 4.5 MW, and the Vestas V-136, a 269-foot hub-height turbine also rated at 4.5 MW, or comparable models.

The wind project includes a range of infrastructure to support operations:

  • 34.5 kilovolt (kV) underground collection lines

  • A supervisory control and data acquisition (SCADA) system

  • Up to four temporary and two permanent meteorological towers (METs)

  • Access roads

  • Temporary construction laydown and staging yards, construction trailers, and parking areas

  • An operations and maintenance facility to be located in Laramie County

Next Steps on Wind in Laramie County

The Board of County Commissioners will make the final determination on the Class C Conditional Use Permit. A public hearing before the board is scheduled for Tuesday, December 1, 2026, at 3:30 p.m.

A second hearing on the project's Site Plan for wind is tentatively scheduled for Tuesday, December 15, 2026. That hearing depends on the conditions that the County Commissioners place on the Conditional Use Permit.  

Next Steps for Solar in Laramie County

  • Industrial Siting: Wyoming's industrial siting process is a state-level review of large energy facilities. It looks at how a project could affect the surrounding community, including local services, roads, and housing. The Chalk Bluffs expects to submit its application in March 2027, with hearings in August 2027.

  • Solar Permit: This county Conditional Use Permit would cover any solar facilities proposed in Laramie County. Like the wind permit, it would go before county officials at public hearings. Chalk Bluffs expects to submit this application in Spring/Summer 2027, with hearings in the fourth quarter of 2027.